Project Description
The present district office and training facility is at the end of life cycle requiring increased maintenance costs, the office is located on Airport Road.Project Location
25490 Airport Rd, Punta Gorda, FL 33950Project Impacts
Additional work is being conducted with the fill material due to high moisture content, all testing is coming back as passed inspection. 2/2/24Latest Updates
The foundation footers and stem walls are complete. Install of roof drains, interior floor plumbing and interior floor electrical conduits are being installed now.
Budget
Phase | Cost |
---|---|
Design | $1,000,000 |
Construction | $8,300,000 |
Total Budget | $9,300,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/11/2021 | 08/15/2022 | 03/17/2022 |
Design Development | 08/15/2022 | 04/13/2023 | 04/14/2023 |
Construction | 10/04/2023 | 06/17/2025 | |
Turnover & Closeout | 06/17/2025 | 07/17/2025 |
Project Phase
Construction
Last Updated
03/08/2024
Project Manager
Gary Burdahl
Public Relations
Brian Gleason
Email Public Relations
Project Number
c892102
Sponsor Department
CCSO
Design Engineer/Architect
Schenkel and Shultz Inc.
Construction Contractor
Wharton-Smith Inc.